Beginning Monday, June 8, APAC Shears of Salina will place an asphalt overlay on Broadway Boulevard from Republic Avenue to 9th Street. This work is expected to continue throughout the week, weather permitting.
Also on Monday, crews will begin milling operations on Wayne Avenue from Highland Avenue to 4th Street. Milling will then continue on Ohio Street from Cloud Street to Belmont Boulevard for the remainder of the week.
Traffic will be maintained through the work zones; however, lane restrictions will vary by street. On multi-lane streets, one lane of traffic in each direction will remain open. On two-lane streets, including Wayne Avenue, traffic will be reduced to a single open lane. Motorists should expect minor delays and are encouraged to slow down and use caution when traveling through work zones.
Additional streets included in this project are:
• Clay Ridge Court
• Vortex Avenue – Scanlan Avenue to Centennial Road
• Wall Street – Centennial Road to the west cul-de-sac
• Schippel Drive – Ohio Street to Lewis Street
• Fawn Street – Cloud Street to Schippel Drive
• North 9th Street Frontage Roads – North of Thomas Park
This work is part of the City of Salina’s 2026 $5.9 million street maintenance capital improvement program.