On Wednesday, September 18th through Friday, September 20th, APAC Shears of Salina will continue work on the City of Salina’s annual asphalt Mill and Inlay project. The schedule is as follows, weather permitting:
Cloud, from Westwood to Broadway
The work on Cloud Street, consists of milling the current asphalt road surface and an inlay of 1-1/2”.
The work will be completed with road closure to through traffic but will allow for residential access. Motorists should expect modest delays and are encouraged to avoid the work zones altogether if possible. Through traffic is encouraged to avoid the area and utilize different routes.
The scheduled work mentioned above is the seventh installment of the City of Salina’s 2024 Mill and Inlay annual maintenance project. The full project cost of all installments totals $1.17 million