MILL
AND INLAY WORK CONTINUES
On Wednesday through Friday, November 13
through 15, APAC Shears of Salina will continue work on the City of Salina’s
annual asphalt mill and inlay project.
The schedule is as follows, weather permitting:
Milling:
|
M
|
T
|
W
|
TH
|
F
|
|
11
|
12
|
13
|
14
|
15
|
Ninth, Crawford to Walnut
|
M
|
T
|
W
|
TH
|
F
|
The work consists of
milling the existing asphalt street surface 1.5” and replacing it with new
asphalt to rehabilitate and preserve the pavement section. Permanent pavement markings will be placed
shortly after the resurfacing.
The work will be
completed with lane closures. Motorists
are encouraged to seek alternate routes to their destinations.
The $1.5 million project
is a major component of the City of Salina's $4.7 million 2019 maintenance
capital improvement program.