Beginning Tuesday, July 1, 2025, Smoky Hill Construction will be working in the intersection of Marymount Road and Glen Avenue. Pavement will be removed, existing utilities will be located, and a new water main will be installed. Eastbound Glen Avenue will be closed to traffic from Marymount Road to Aullwood Road. Northbound Marymount Road will be reduced to one-lane through Glen Avenue. Access to adjacent properties will be maintained. Work is expected to last four weeks and be completed by July 29, weather permitting.
Appropriate barriers will be in place to ensure the safety of workers. Motorists may encounter minor delays and are encouraged to find alternate routes.
For additional information, please contact the City of Salina Utilities Department at (785) 309-5725.