5/24/2018 - Microsurfacing Work Continues
On Monday through Friday, May 28-June 1, Vance Brothers of Kansas City, Missouri will begin resurfacing the following City of Salina streets, weather permitting:
|
M
|
T
|
W
|
TH
|
F
|
|
28
|
29
|
30
|
31
|
1
|
Derby St, Foxboro Dr to End
|
M
|
T
|
W
|
TH
|
F
|
Charles St, Phillips to 11th
|
M
|
T
|
W
|
TH
|
F
|
Elmore Dr, Crawford to Prescott
|
M
|
T
|
W
|
TH
|
F
|
Guernsey, Prescott to Front
|
M
|
T
|
W
|
TH
|
F
|
Morrison, Montrose to College
|
M
|
T
|
W
|
TH
|
F
|
Morrison, 10th to 9th
|
M
|
T
|
W
|
TH
|
F
|
Westchester, Ohio to YMCA Dr
|
M
|
T
|
W
|
TH
|
F
|
Elm, Santa Fe to Ohio
|
M
|
T
|
W
|
TH
|
F
|
Mellinger Dr, Ohio to Roach
|
M
|
T
|
W
|
TH
|
F
|
Aidan, Beginning to River Trail
|
M
|
T
|
W
|
TH
|
F
|
Brock, Ohio to End
|
M
|
T
|
W
|
TH
|
F
|
Blakemoore East side, Lakeview to Sierra
|
M
|
T
|
W
|
TH
|
F
|
Calcutta, Lakeview to Sierra
|
M
|
T
|
W
|
TH
|
F
|
Falconview, Wayne to Eaglecrest
|
M
|
T
|
W
|
TH
|
F
|
Shalimar, Magnolia to Wayne
|
M
|
T
|
W
|
TH
|
F
|
Linden, Sequoia to Wayne
|
M
|
T
|
W
|
TH
|
F
|
Minneapolis, Osborne to Santa Fe
|
M
|
T
|
W
|
TH
|
F
|
Tanglewood, Saddlebrook to River Trail
|
M
|
T
|
W
|
TH
|
F
|
Twin Oaks, Carolina to End
|
M
|
T
|
W
|
TH
|
F
|
Roads will be closed to traffic during construction for a period not to exceed 8 a.m. to 5 p.m. Residents will be provided sufficient notice of closures and special requests will be accommodated.
Microsurfacing is a common method of pavement surface treatment which consists of a polymer modified asphalt slurry (about 3/8 inch thick) that coats the pavement surface and creates a smooth moisture-resistant barrier. It also increases ride-ability and seals smaller cracks. When combined with proper pavement sealing, microsurfacing extends the service life of the roadway. Streets are estimated for microsurfacing on a 6 to 8 year cycle. This year's project covers approximately 35 lane miles of primarily local City of Salina roads.
The $750,000 project is a major component of the City of Salina's $4.7 million 2018 maintenance capital improvement program.