Mill and Inlay Work Continues
During the week of October 30 – November 3, APAC-Kansas, Inc., Shears Division of Salina will continue work on the City of Salina’s annual Asphalt Mill and Inlay project.
The schedule is as follows, weather permitting:
|
M
|
TU
|
W
|
TH
|
F
|
Indian Rock, Ohio to Indiana
|
|
|
|
|
|
Kansas, Iron to Elm
|
|
|
|
|
|
Center south of Oakdale Park
|
|
|
|
|
|
Columbia, Ash to Elm
|
|
|
|
|
|
Woodland, 9th to 11th
|
|
|
|
|
|
12th, Crawford to Prescott
|
|
|
|
|
|
Roach, Albert to Cloud
|
|
|
|
|
|
Marcella, Schilling through Huehl Circle
|
|
|
|
|
|
The work consists of milling the existing asphalt street surface 1.5" and replacing it with new asphalt to rehabilitate and preserve the pavement section. Permanent pavement markings will be placed shortly after the resurfacing.
The work will be completed with lane closures. Residents and business owners will be notified prior to changes in access to properties. On-street parking in work zones will be prohibited. Any vehicles or equipment left on the street on the day paving is scheduled may be towed at the owners' expense.
The $1.5 million project is a major component of the City of Salina's $4.7 million 2017 maintenance capital improvement program.