2/24/2017 - 2017 Pavement Sealing Update

Contact: Bill Shelby
Public Works Department
(785) 309-5725
bill.shelby@salina.org
2017 Pavement Sealing Update
On Monday, Feb 27 through Friday, Mar 3, APAC Shears of Salina will continue performing the annual pavement sealing maintenance on the following streets for the City of Salina, weather permitting:
Mon, Feb 27
|
Each street around the BiCentennial Center including the Midway
|
Colton Court, 400’ West of Christy to Christy
|
Christy, Colton to Cloud
|
Sky, 200’ West of Christy to Christy
|
Tues, Feb 28
|
Eileen, Caywood to Melanie
|
Marla, Melanie to cul-de-sac
|
Melanie, Schilling to North of Rittgers
|
Wed, Mar 1
|
Jack, Caywood to Caywood
|
Thurs, Mar 2
|
Piercy, Ohio to end
|
Joanie, Linda to Melanie
|
East Ash, Ohio to River Place
|
Connecticut, Gypsum to Iron
|
Gypsum, Wisconsin to Indiana
|
Stack, Delaware to Missouri
|
Indian Rock, Indiana to Ohio
|
Fri, Mar 3
|
Roach, Belmont to Wayne
|
Rittgers, Linda to Melanie
|
Delaware, Indian Rock to Greeley
|
“Road Work Ahead” signs will be placed in advance of active work zones, and temporary single-lane closures are to be expected. Motorists are asked to proceed with caution when approaching work zones for the safety of the crews performing the work. Access to properties within work zones will be maintained at all times.