2016 Chip Seal Road Work Continues
On Monday, July 18th, City contractors plan to chip
seal various streets in Salina. The schedule is as follows:
Monday
July 18
|
3rd Street – Pacific Avenue to Euclid Avenue
Bailey Court
Jumper Road
Kneubuhl Court
Rogers Court
Sutherland Court
Wall Street
|
The work will include applying the asphalt surface
treatment and placing temporary pavement markings.
The
contractor will begin setting traffic control at 7 am. Temporary traffic
control and flaggers will be present to direct vehicles through the work zones
and maintain traffic flow; traffic will be reduced to single lanes in both
directions during paving. Residences and businesses
will be notified if access to driveways will be restricted while work is
performed. On-street parking in work
zones will be prohibited. Any vehicles or equipment left on the street the day
work is scheduled may be towed at the owners expense.
Chip sealing is a method of pavement surface treatment
which prolongs the serviceability of streets by sealing the surface. Combined
with joint and crack sealing, this surface treatment program extends the
service life of pavement.
For
additional questions, contact the Department of Public Works at 785-309-5725.