7/8/2016 - 2016 Chip Seal Road Work to Begin
Contact:
Kent Johnson, Civil Engineer
(785) 309-5725
kent.johnson@salina.org
2016 Chip Seal Road Work to Begin
Beginning on Monday, July 11th, City contractors will begin chip sealing on various streets within the city limits. The schedule for July 11 – 15 is as follows:
Monday
July 11
|
Airport Road – inside Salina city limits
Bailey Court
Clay Ridge Court
Jumper Road
Kneubuhl Court
Rogers Court
Sutherland Court
Vortex Avenue
Wall Street
|
Tuesday
July 12
|
Arnold Court
Berschel Avenue
Hein Avenue
Scanlan Avenue – north of Tony’s Road
|
Wednesday
July 13
|
3rd Street – Pacific Avenue to Euclid Avenue
Diamond Drive – in front of Motel 6 and IHOP
Monarch Road
Thomas Park
|
Thursday
July 14
|
Old 40 Highway – inside Salina city limits
Old 40 Highway Court
Pacific Avenue – Kenny’s Autos to Ohio Street
Pacific Court
|
Friday
July 15
|
Bromac Avenue
Dewey Street – west of Bromac Avenue
Edison Place
Lakewood Park Drive and Parking Lots
|
The work will include applying the asphalt surface treatment and placing temporary pavement markings.
The contractor will begin setting traffic control at 7 am. Temporary traffic control and flaggers will be present to direct vehicles through the work zones and maintain traffic flow; traffic will be reduced to single lanes in both directions during paving. Residences and businesses will be notified if access to driveways will be restricted while work is performed. On-street parking in work zones will be prohibited. Any vehicles or equipment left on the street the day work is scheduled may be towed at the owners expense.
Chip Sealing is a method of pavement surface treatment which prolongs the serviceability of streets by sealing the surface. Combined with joint and crack sealing, this surface treatment program extends the service life of pavement.
For additional questions, contact the Department of Public Works at 785-309-5725.