Contact our office at (785) 826-7340, at least 24 hours in advance of the requested inspection date and time.
The following information must be provided when calling for an inspection:
A. Permit number
B. Name and address of project
C. Fire protection contractors company name
D. Contact name and phone number
E. Type of inspection requested
A representative of the company requesting the inspection must be present at the time of inspection.
FMO approved, stamped and signed plans must be kept on the job site and presented to the inspector upon request. Contractor shop drawings are not considered approved plans.
On-Site Permit Requirements
Keep plans and permit on the job-site at all times during the construction process.
The Fire Marshal and/or field inspector may request additional inspections as necessary.
Final Inspection
This inspection shall be conducted when all Sheetrock and millwork is completed. The objective of this inspection is to verify device coverage is still adequate after the initial rough inspection. This will enable the Salina Fire Marshal's Office and the fire protection contractor the ability to make necessary changes prior to the request for the Certificate of Occupancy.
Governing Documents
All tests and installation must comply with, but not limited to, City of Salina Code Chapter 14, The International Fire Code 2006 Edition and applicable NFPA Codes.
|